Belgium - 2019 - Other
11 Crane runway girders Hall KLM ArcelorMittal Ghent
Completed projects
You are here
11 Crane runway girders Hall KLM ArcelorMittal Ghent
On behalf of ArcelorMittal, Victor Buyck Steel Construction fabricates and assembles 11 new crane runway girders in hall KL and LM to replace existing crane runway girders. The crane runway girders have a weight that varies between 35 and 45 t and a length of 20 m. The most important activities are the removal of the old girders and the assembly of the new crane runway girders. This happens during a standstill of the production hall for 168 hours
Project type & location
Type:
BridgesCategory:
Heavy industrial steelwork Function:
Crane runway girdersCountry:
BelgiumLocation:
GhentProject start date:
Project finish date:
Project specifics
Dimensions:
11 x 20m x 2.9m (LxW)Tonnage:
456 tClient(s):
ArcelorMittal BelgiumSteel Construction:
Victor Buyck Steel Construction